Portfolio





Projects



South Project Alliance (SPA) – Part of the level crossing removal Project – re-Signalling of Carrum – Frankston of the Frankston line from relay interlocking to CBI (Smartlock2oo3GP, SMARTIO, RAILVIEW and TCS) – April–July 2019

Caulfield to Dandenong (CTD) – December 2018 & April 2019

Rail Infrastructure Alliance (RIA) – January – April 2019

North East Project Alliance (NEPA) – February 2019

North West Project Alliance (NWPA) – Reservoir, High street - November 2019

South Project Alliance (SPA) – Part of the level crossing removal Project – re-Signalling of Carrum sidings – 3 – 29 Feb 2020

North East Project Alliance (NEPA) – Part of the level crossing removal Project – April 2018

Cross Yarra Partnership (CYP) – May 2018

Ballarat Line Upgrade (BLU) – June 2018

Caulfield to Dandenong (CTD) – August 2018

Burke Road (Heyington Dark Territory) - Coverage of the dark territory portion on Burke Rd (03 GAR VIXL). The remaining portion of the dark territory between Burnley and Kooyong needed to be covered and related indications transmitted to Metrol (MTM) panel.

V/Line C/Light Removals

Mernda Rail Extension Project - The Mernda Rail Extension Project involved the development of a new 8km-long dual rail line to link the existing South Morang line with Mernda in Melbourne, Australia. The project also included construction of three new stations at Mernda, Marymede and Hawkstowe. The A$600m ($453m) extension project was funded entirely by the Victorian State Government. Construction on the project commenced in April 2017 and was completed in August 2018, six months ahead of the schedule.

North West Project Link (Sydney Trains)

Burke Road (Glen Iris Grade Separation)

RRL SP6 SSSTS

V/Line Driver Training Stage

V/Line Early Activation Stage

V/Line Southern cross SST Migration Stage 1, 2 & 3 - Migration of North and South CBI data from SSI to Alstom SML400T (Installation of Smartlock 2oo3, Support System maintenance panel, FEP (Front End Processor), Trackside Interface Communication Cubicle (TICC)

V/Line WPA – VS3

V/Line WPA SP2 Stage 2.10

Work Package B; SP6 South Kensington (SKN) Split - Commissioning of CBI data and PICVIEW (MTM visibility of V/Line area) - interface boundaries between V/Line and MTM

SKN Telemetry Stage 1,2,3

North Melbourne Flyover

KRESP Stage – Occo 50B

SP7 Occo 56 (WP –B)

Sydney ETCS Level 2